Greetings to you all!
Today marks mid week,the half way slump the steam just starts to run out.
Today was a tough day at the Trinity with no supplies yesterday and goals that I (not the group) would like to have seen get done makes you appreciate the group you are with for support.
It's funny how when you go on a mission trip you ask yourself "whats your purpose" what's your reason ?
If you remember from a few weeks ago when I asked "what's your purpose"? Well, today I know my purpose this trip is to get as much done (a goal) that I can in just one week,and sometimes that's not Gods purpose. So I can be thankful that the crews we have are great workers,they love their Lord and love to serve,amen!
Today's progress we completed the sanctuary floor to about 90%. The back needs to be done about 33"X35'.The grouting is about 70% complete on the same area.
Tomorrow the plan will be to finish the grouting we have and move the operation to the front entry way and the bathrooms and complete the grouting by Friday afternoon.
Thursday marks our last full work day as we prepare to wrap it up on Friday and head back to Illinois.
As you look at the pictures you can see the work that was done today.
So that wraps it up for today my knees are sore and wrist hurt as well but it;s all good!
Today marks mid week,the half way slump the steam just starts to run out.
Today was a tough day at the Trinity with no supplies yesterday and goals that I (not the group) would like to have seen get done makes you appreciate the group you are with for support.
It's funny how when you go on a mission trip you ask yourself "whats your purpose" what's your reason ?
If you remember from a few weeks ago when I asked "what's your purpose"? Well, today I know my purpose this trip is to get as much done (a goal) that I can in just one week,and sometimes that's not Gods purpose. So I can be thankful that the crews we have are great workers,they love their Lord and love to serve,amen!
Today's progress we completed the sanctuary floor to about 90%. The back needs to be done about 33"X35'.The grouting is about 70% complete on the same area.
Tomorrow the plan will be to finish the grouting we have and move the operation to the front entry way and the bathrooms and complete the grouting by Friday afternoon.
Thursday marks our last full work day as we prepare to wrap it up on Friday and head back to Illinois.
As you look at the pictures you can see the work that was done today.
Jenn & Ryan grouting
Zach this one's for you!
End of the day shot from the AV room
Lower angle
The choir loft
Prayers
Continued safety for all the workers at trinity
Thanks for all current and past who have worked out of Camp Restore
It's been a long hard day and hot 80ยบ and Im exhausted so till tomorrow night!
In HIs Grip
Lark